|
Troubleshooting
Made simple with out a design
At the Bottom of the Foundation Wall Water or moisture
on the top of Bottom Wall Plate and/or high humidity
in the basement.
Causes:
a.
No Sump.
b.
No or too little gravel under the floor or under the
footing plate or floor.
c.
There is something damming the water under the floor
or under the footing plate.
d.
The Vapor Barrier has been extended under the footing
plate.
e.
The Vapor Barrier has not been cut off at the bottom
of the footing plate, but is instead extended into the
gravel.
f.
The Vapor Barrier has been left off the Wall or omitted
under the floor.
g.
The bottom of the sump has not been perforated or open
to the gravel.
h.
The sump is not drained to a positive drain (by gravity
or pump).
i.
The sump is not surrounded with at least 4 inches of
gravel.
Foundation
wall sinks out of level at any point along the foundation
wall.
Causes:
a. The axial load is too heavy for the size of the footing
plate.
b.
There is not enough gravel depth or width under the
footing plate.
c.
There is too much building weight for the gravel depth
under the footing plate (gravel shear). note this can
happen only with undersize footing plates.
d.
The footing plate is too wide giving rise too induced
tension. (oversize footing plates)
e.
Plywood stiffener is too thin.
f.
Plywood stiffener face grain is not perpendicular to
footing plate grain.
g.
Plywood or concrete concentrated load pad is missing
or too small for the point load.
h.
The load pad is not thick enough for the concentrated
load.
i.
If a plywood pad, the adjacent pieces are not perpendicular
to each other.
j.
If a plywood pad, the adjacent pieces are not glued
together.
k.
The footing plate is plywood, the adjacent pieces are
not perpendicular only when required, are not enough
layers thick, are too wide, or are not glued together
as required by some designs.
L.
The footing plates has been installed on a mixture of
stone and snow. This will cause the house to sink when
the temperture warm up. The Installer of the footing
plates must check for this condition before installing
the footing plates. A snow and stone mixture will be
below 3000 lbs per sq. ft. A 3000 lbs. per sq. ft. stone
footing is required by the pwf design.
The foundation wall is bowed, out of plumb, or deflecting
inward.
Causes:
a.
There is not enough bearing against the floor by the
bottom edge of the studs.
b.
The grade for the species used for studs is too low.
c.
The spacing of the studs is too great.
d.
Insufficient number and/or size and diameter of nails
used to nail bottom top plate to studs.
e.
The grade for the species used for top plates are too
low.
f.
Nail spacing is too far apart and/or size and diameter
of nails used to nail the two top plates together.
g.
Nail spacing is too far apart and/or size and diameter
of nails used to nail band joists to top plates.
h.
Floor joists not adequately attached to the band and
the top plates (this may be done with pwf framing straps,
joist angles, or joist hangers---The number of nails,
size, and diameter is significant for each type of framing
anchor).
i.
Shear wall(s) may be needed.
j.
The length of the shear wall(s) may be too short.
k.
The nail spacing at the plywood panel edges of the shear
wall(s) may be too far apart at the plywood panel edges,
and/or the nails are the incorrect length or diameter.
l.
Horizontal blocking may be left out at a horizontal
plywood joint in the shear wall.
m.
Holes were drilled in the tension half of the stud or
near the point of maximum moment.
n.
At end walls where the floor joists run parallel to
the foundation wall, blocking between the 1st, 2nd,
etc. interior joist space(s) may have been left out
or removed for ducts, pipes, wires ,etc. The block spacing
is significant.
o.
In all blocked joist spaces the minimum joist spaces
must be at least as wide as the blocks are high.
p.
The sub-floor above the foundation may not have been
nailed to the 1st, 2nd,etc. interior joists at the correct
nail spacing; or the correct number of nails were not
used to nail the sub-floor to the blocks; or the nails
are not the correct length or diameter.
q.
The sub-floor is not a rated sheathing.
r.
When a stairwell or other opening is in the floor-ceiling
diaphragm, adjacent to and less than 4 feet from a foundation
wall with a backfill, the top plates of the wall become
a horizontal beam. Depending on conditions, the beam
is constructed by adding plates to the top and thru-bolting
all the plates together. The lateral load on the beam
is blocked into the floor/ceiling diaphragm through
headers to the inside of the opening. If this is not
done correctly the top of the foundation wall will deflect
into the opening. The grade, species, and size of the
top plates are significant in determining the number
of pieces to us for the beam. The size of the bolts
are important in order to determine the spacing of the
bolts. All bolts used in wood foundations should always
be hex-head machine bolts with washers. (Never use carriage
bolts).
The wood basement wood floor is up-lifting or sliding
or sinking.
Causes:
a. Uplifting: The lateral soil loads at the bottom of
opposite foundation walls are
forcing the wood floor to rise near the center. A short
kneewall under the floor joists and
connected to the floor joists will correct this. Also,
bearing walls, shear walls, partitions, or posts on
top of the floor will do the same thing.
b.
Sliding: This can occur when a high backfill is opposite
a walkout wall. Sliding can occur if there is no frost
wall or anchor wall under the walkout wall; or if the
wood floor is not adequately connected to the top of
the frost wall. Nailing patterns become significant
at the bottom of the walkout wall where it connects
to the frost wall.
c.
Sinking: This occurs when the spacing between the sleepers
is too wide for the width of the floor joists or floor
joist spacing, or if the sleepers themselves are too
narrow in width to adequately transfer the floor load
to the gravel and ultimately to the bearing soil; or
if there are no sleepers and the floor joists rest directly
on the gravel under the floor.
d.
Uplifting near walls: The plywood floor system has not
been cut back 1/4" away from all wall studs.
e.
Center barring wall: Walls are not supported by the
correct size tee under the wall.
f.
The footings, sleepers and support tees are installed
on a mixture of stone and snow. This mixture will not
support the axial load to the bearing soil.
Help
Desk 810 955-4305
For
more information:
www.woodbasement.com
www.woodfoundation.com
Note:
Panel foundations can be site built or made in a
shop. When made so it cover up items that need inspection
by the Building Inspector. Third Party Inspection may
be required. (inspect for grade stamps, treatment stamps,
stud spacing, insulation, nailing, dip of saw cuts,
plywood requirments are some of the item that a third
party inspection will note.
All
Panel Wood Foundations must be designed and installed
in accordance with:
All current Building Codes Standards
While
wood foundations are easy to build, this is only true
if one is building from an accurate well designed plan.
When such a plan is incorrect, or if something is left
out of the plan or absent, or if a design is made using
a guide manual (these are not design manuals); major
mistakes can be made during the construction process.
These errors cause problems for the owner, builder,
and the building department.
pwfs.com a service of Permanent Wood
Foundation System (PWF), supported by Southern Pine
lumber users affiliated with the training and installation
of wood foundations.
.
.
|